Home Inspection Survey Building Overview
Home Inspection
Survey Building Overview
Surrounding situatiou of the site. Kyoto city
Inspection implementation date Junuary 9 2023
Building structure wooden house
two-story house
Total area 145sq m
![](/kanri/editor/kcfinder/upload/images/%E5%90%8D%E7%A7%B0%E6%9C%AA%E8%A8%AD%E5%AE%9A-2%288%29.jpg)
Current Situation
This house was constructing about 45 years ago.
context of inspection
①Check vertically and horizontally with an infrared spirit level.
②Visual inspection.
③ Inspection in the wall used by microscoop.
![](/kanri/editor/kcfinder/upload/images/%E5%90%8D%E7%A7%B0%E6%9C%AA%E8%A8%AD%E5%AE%9A-4%287%29.jpg)
"This house has some serious problem, for instance , I found many cracks on the outer wall and foundation. maximum wide is about 2mm, it is too serious problem. And, I measured horizontal and lean. The pillars were tilted by about 2mm to 14mm. The position of pillar and crack is the
almost same. I think this fenomenon is ground sabsidence.
It is nececcery to repracement and reforcement of the foundation."
Cost
Preview fee $0
Technical fee
$5.00 × 145sq m =$725.00
Bace Fee $4.00 × 145sq m =$580.00
Tax $130
Total $1,435
Request from client
Building collpse degree examination cost $4.50 ×145sq m =$652.50
Preparation of building structure reinforcement plan.
$50.00 ×145sq m =$7,250.00
Survey Building Overview
Surrounding situatiou of the site. Kyoto city
Inspection implementation date Junuary 9 2023
Building structure wooden house
two-story house
Total area 145sq m
![](/kanri/editor/kcfinder/upload/images/%E5%90%8D%E7%A7%B0%E6%9C%AA%E8%A8%AD%E5%AE%9A-1%289%29.jpg)
![](/kanri/editor/kcfinder/upload/images/%E5%90%8D%E7%A7%B0%E6%9C%AA%E8%A8%AD%E5%AE%9A-2%288%29.jpg)
Current Situation
This house was constructing about 45 years ago.
context of inspection
①Check vertically and horizontally with an infrared spirit level.
②Visual inspection.
③ Inspection in the wall used by microscoop.
![](/kanri/editor/kcfinder/upload/images/%E5%90%8D%E7%A7%B0%E6%9C%AA%E8%A8%AD%E5%AE%9A-3%289%29.jpg)
![](/kanri/editor/kcfinder/upload/images/%E5%90%8D%E7%A7%B0%E6%9C%AA%E8%A8%AD%E5%AE%9A-4%287%29.jpg)
"This house has some serious problem, for instance , I found many cracks on the outer wall and foundation. maximum wide is about 2mm, it is too serious problem. And, I measured horizontal and lean. The pillars were tilted by about 2mm to 14mm. The position of pillar and crack is the
almost same. I think this fenomenon is ground sabsidence.
It is nececcery to repracement and reforcement of the foundation."
Cost
Preview fee $0
Technical fee
$5.00 × 145sq m =$725.00
Bace Fee $4.00 × 145sq m =$580.00
Tax $130
Total $1,435
Request from client
Building collpse degree examination cost $4.50 ×145sq m =$652.50
Preparation of building structure reinforcement plan.
$50.00 ×145sq m =$7,250.00